Posts tagged Deidre G. Duncan.
Time 1 Minute Read

This week, the U.S. District Court for the Middle District of Louisiana granted a preliminary injunction, halting construction of the $750 million Bayou Bridge Pipeline. Judge Shelly D. Dick concluded that the U.S. Army Corps of Engineers, in authorizing the project, did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction. In addition, the Court found the Corps’ environmental analysis failed to sufficiently consider and address historical impacts to wetlands from similarly situated ...

Time 4 Minute Read

Federal agencies that authorize or permit large infrastructure projects, like interstate natural gas pipelines, are often subject to the requirements of the National Environmental Policy Act (NEPA), and environmental organizations frequently rely on NEPA to challenge a project. The D.C. Circuit recently struck down a decision by the Federal Energy Regulatory Commission (FERC) to approve the construction and operation of three interstate natural gas pipelines because the Court found defects in FERC’s NEPA analysis. The court’s decision to vacate FERC’s authorization now threatens to shut down the pipelines, including the Sabal Trail pipeline currently supplying natural gas to newly constructed power plants in Florida.

Time 1 Minute Read

Once large infrastructure projects, such as oil and natural gas pipelines, receive federal government approval, they are often the target of legal challenges from opposition groups. Opponents repeatedly argue that the environmental review, pursuant to the National Environmental Policy Act (NEPA), was insufficient. If a court finds deficiencies in the government’s NEPA analysis, can a court halt construction or cease operations even after years of project design, permit approvals at all levels of government, and tens of millions of dollars in investment? This question ...

Time 4 Minute Read

In a closely watched case, the United States Court of Appeals for the D.C. Circuit last week dismissed an interstate natural gas pipeline company’s challenge to the State of New York’s delay in issuing a water quality certification under section 401 of the federal Clean Water Act (CWA) for the Millennium pipeline project. While the company requested a ruling that the state had waived its right to make a decision on water quality certification for the project, the court decided to dismiss the action – holding that even if the state agency’s lengthy delays did constitute a waiver under CWA section 401, there was no cognizable injury to the company that would give it standing to challenge the delays in court. Rather, according to the court, the remedy is for the company to present evidence of waiver directly to the Federal Energy Regulatory Commission (FERC) to seek authorization to begin construction of the project. The case is one of several pending across the country that involve a state’s authority to issue, deny, or waive a CWA water quality certification for interstate natural gas pipeline projects.

Time 4 Minute Read

Despite oil already flowing through the pipeline, federal litigation involving the controversial Dakota Access Pipeline (DAPL) took another turn last week when partial summary judgment was granted to tribes challenging the adequacy of the US Army Corps of Engineers’ review of DAPL under the National Environmental Policy Act (NEPA) and other statutes. Two tribes, the Standing Rock Sioux Tribe and the Cheyenne River Sioux Tribe, filed suit in July 2016 attempting to block construction of the last remaining segment and operation of DAPL. As sometimes is the case, agency approvals came faster than the court’s opinion, and without a stay of proceedings DAPL began operating in early June 2017. Having granted partial summary judgment, the court did not require pipeline operations to cease, instead delaying the question of an appropriate remedy until after further briefing by the parties.

Time 3 Minute Read

On February 28, 2017, President Trump signed an Executive Order (EO)  that sets into motion a process for the Administrator of the Environmental Protection Agency (EPA) and the Assistant Secretary of the Army for Civil Works (jointly, the “Agencies”) to review the Obama Administration’s Waters of the US (WOTUS) Rule.  80 Fed. Reg. 37,054 (June 29, 2015). The EO directs the Agencies to review the WOTUS Rule for consistency with the Clean Water Act (CWA) and the policies set forth in the EO, stating that “[i]t is in the national interest to ensure that the Nation’s navigable waters are kept free from pollution,” while at the same time “promoting economic growth, minimizing regulatory uncertainty, and showing due regard for the roles played by Congress and the States under the Constitution.”  Following review, the EO instructs the Agencies to publish, as appropriate, a proposed rule for notice and comment rescinding or revising the WOTUS Rule.

Search

Subscribe Arrow

Recent Posts

Categories

Tags

Authors

Archives

Jump to Page